FOR INDUSTRY

Adapt auxiliary equipment to your production needs

A pump keeps running at the same rate during waits, a setpoint is entered by hand, or data from a remote point is missing. With D.System and its MiJ-Air extension we review a clearly bounded auxiliary unit or process and define what we can control, automate or monitor.

A specific installation, with its existing protections and safety controls.

Applications with a defined scope

01

A pump that has to follow demand

In a real, anonymised case on a coil line, D.System received the loading or unloading phase and the operator's recipe. The control applied the pressure setpoint and a variable-speed drive adjusted the motor, keeping a minimum safety pressure during waits. This allows a comparable case to be studied; it does not prove savings for another installation.

02

Compressed-air readings that need monitoring

Readings of consumption and pressure with history and charts are already in operation. MiJ-Air sends the readings to D.System. The alerts are running in a pilot installation. Acting on equipment, additional reports and analysis of possible leaks are studied as extensions, each with its own validation.

03

Data that is keyed into a machine again

In integrations already carried out, the production system delivers an order as a CSV or XML file. Our program validates the data and prepares the configuration; an incomplete order is held and the operator is notified. For another machine, the format, permissions, signals and error handling are reviewed.

Control and integration on the existing installation

Together with your installer and maintenance staff we review the equipment, signals and existing control. D.System provides the control and automation logic for the agreed scope. We identify which functions are kept, which are recovered and how the action is coordinated with the PLC or other systems in place.

MiJ-Air is D.System's LoRa extension: it carries readings from distributed points to D.System and relays the commands D.System determines. It allows less communication wiring to be considered where coverage and response times are adequate.

Protections, safety controls and fast operations remain under the machine's local control. Coverage, power supply, permissions, data refresh and the response to loss of communication are checked. Any interventions and stoppages needed are planned with the plant.

A first step that can be accepted and maintained

We choose a unit, a point or a function. The phase must deliver a useful result even if it is never extended: an agreed regulation, a reading you can consult, or a preparation task that is automated and verified.

The proposal lets maintenance, production and engineering review the problem, the signals available, the dependencies and who is responsible for what. We agree scope, price, timescale and tests before any work starts. If a detailed technical study is needed, it is quoted with a defined deliverable.

Functional tests verify commands, responses, limits, data and behaviour under failure. To verify energy savings, measurements and comparable conditions of load, product and operating hours are agreed. Correct readings or control do not in themselves prove savings.

Deployment with the professionals you trust

Deployment is carried out with your installer. We define the solution, coordinate the integration and verify operation. Your installer takes part in the layout and carries out the assembly.

We deliver the equipment needed, configured and programmed in advance when the project requires it, together with its documentation and hands-on training for the installer and the maintenance staff.

We agree the technical support included, the contact channel and how an incident is reported, reviewed and closed. This way the professionals in charge know the installation and can act with our backing, within the agreed scope.

Learn more in the video

6 min 33 s · Audio in Spanish · Optional subtitles · Illustrative images

The video explains the pump case, the connection of distributed points and a first step with a defined scope. It distinguishes between the compressed-air readings in operation, the alerts in pilot and the commissioned development of a quality-control application.

Read the transcript

Hello, and thank you for giving me these few minutes. With D.System and its LoRa extension, MiJ-Air, we work so that equipment responds to what production needs. We will go through a real case, how to connect distributed points and how to define a first improvement in your plant.

In many plants, production changes pace, but the auxiliary equipment keeps running the same way. A pump keeps running at a high rate during a wait, a pressure is not adapted to the product or an order is entered again by hand. In addition, some points are far from the panel, and cabling them is costly. The first step is to identify the equipment, the problem and which decision is worth improving.

On a coil line, we adapted a hydraulic pump to demand with D.System. The system received the loading or unloading phase and the recipe chosen by the operator. The control applied the pressure setpoint and a variable-speed drive adjusted the motor speed. During waiting periods a minimum safety pressure was maintained. Consumption before and after was compared with a power analyser. The customer also noticed less noise and oil heating, without quantifying those observations with formal measurements.

This approach can be used to study other auxiliary equipment: pumps, ventilation, process cooling, water or tanks. The question is when it needs to work, how hard, and which signals make it possible to decide. We review the process, its limits and the compatibility of the control. If the equipment is spread around the plant, we also need to bring its data to D.System.

MiJ-Air is the wireless extension of D.System for connecting those points over LoRa. It collects the readings and takes them to D.System, which manages the data and determines the actions. When the project includes remote actuation, the command comes from D.System and MiJ-Air passes it to the equipment. Its advantage is reaching places that are costly to cable and that may be within LoRa range. That way we can extend the installation with less communication cabling. We check coverage and response times for each function. Protections and fast operations remain in the machine's local control.

In compressed air, reading consumption and pressures is already working, with history and charts. MiJ-Air takes the readings to D.System, where we follow how they evolve. Alerts for low pressure, high temperature or stopped equipment are running in a pilot installation. Further extensions can then be considered: studying idle consumption, preparing reports or acting on equipment with commands from D.System, depending on the project's scope and validation.

We can also make use of the information the company already has. In integrations already carried out, the production management system left an order in a shared folder as a CSV or XML file. Our program validated the data and prepared the machine configuration. If information was missing, the order stayed pending and the operator was notified. Depending on the scope, production results were sent back. We agree the format, updating and error handling to integrate that exchange with the process.

In quality, we have been commissioned to develop further a verification application that already runs guided tests and records results. It will add identification by serial number, an automatic report and guided selection of the configuration. These functions will make it possible to reduce errors and manual checks, and keep the traceability of each unit. The application is standalone and reuses D.System components to make it easier to maintain.

To tackle these improvements, we review with your installer and the maintenance staff what already exists. We can keep useful equipment, integrate compatible signals or recover control functions. With MiJ-Air we extend the reach over LoRa where the cost of cabling makes it hard to add new points. D.System holds the control logic. We agree who operates each function and how the installation responds if communication is lost. The work focuses on what adds value and can be maintained afterwards.

Deployment is carried out with your installer. We define the solution, coordinate the integration and verify operation. Your installer takes part in the layout and carries out the assembly. We deliver the equipment needed, configured and programmed in advance when the project requires it, together with its documentation and hands-on training for the installer and the maintenance staff. This way, the professionals in charge know what has been installed, how it works and what to do in the event of an incident, with our technical support according to the agreed scope. That way we make use of existing resources, avoid duplicating work and make future maintenance easier.

Before carrying out the work, we define what improvement we are after and how to verify it. It may be a more suitable response from the equipment, less set-up time, fewer errors or lower consumption. Functional tests confirm that the system does what was agreed. Energy savings require measurements and defined comparison conditions. We also weigh the installed cost of the LoRa link against the wired alternative. With the total cost and the hours of use, the return on investment can be studied.

The proposal is to start with a first step with a defined scope. You tell us about the equipment or process and we review with your installer and the maintenance staff the signals available. That is how we pin down the problem and how to act in the plant. If we need LoRa, we check how to connect it. A detailed technical study, when needed, is quoted as a phase. We then agree scope, price, timescale and acceptance tests. Once the result has been verified, you will have a basis for deciding what to extend.

If you have equipment that consumes during waiting periods, remote points you need to connect or data that is still copied by hand, tell us about it. You can write to us, visit the website or scan the code shown on screen. We review it with you and your installer to assess which first step makes sense. Thank you for your time.

Before any work starts

Does the PLC or the whole installation have to be replaced?
The case is reviewed with maintenance and the installer. The proposal identifies what is reused and what has to be adapted. PLC access, permissions and interfaces are checked for that installation.
Does MiJ-Air control anything on its own?
No. D.System holds the control logic and determines the commands. MiJ-Air relays them when the function is included. Safety and fast operations stay under local control.
What happens if a reading or communication is lost?
We define what stays under local control, which function is suspended and how the person in charge steps in. That behaviour is tested within the scope. Support and incident handling are agreed before commissioning.
What savings can we expect?
Energy verification requires measurements and comparison conditions agreed for your equipment. In the pump case, consumption was compared with a power analyser; those results do not carry over to another installation.

Tell us which auxiliary unit or process you need reviewed

Tell us what is happening, which equipment is affected and who knows how it works. If a stoppage or refurbishment is planned, let us know. You don't need to send all the diagrams or have a solution in mind yet.